We would like to share with you our last update for this year. The project is nearing completion, with only a few outstanding activities remaining. We would like to take this opportunity to wish you all a Merry Christmas and a Happy New Year. More updates will be shared soon. Kind regards, Niksen...
2025
Weekly Update: 1st–5th December This week, the following works have been completed: Wardrobes:The wardrobes for the two bedrooms have now been installed and finalised. Dividing fence:Construction of the fence dividing the two dwellings has commenced. General electrical works:Tasks including the cooktop installation, electrical conduits for the air-conditioning unit, and the remaining...
Weekly Update: 24th – 28th November This week, the internal painting has been completed, and we wanted to share the current progress in a short video: Week 16 Planning: Next week, we will continue installing the bathroom vanities and finalise the internal plumbing and electrical fit-outs. We will continue to keep you updated as the works progress. Kind regards, Niksen Time...
Weekly Update: 17th – 21st November This week, the following works have been completed: Bathroom Tiling: Tiling has been completed and the vanities are ready for installation. Patio Tiling: Patio tiling has been finalised. Electrical Works: Conduits for the main and second dwelling have been completed. North Fence: Works have been finalised, and the dividing fence is scheduled to...
Weekly Update: 10th – 14th November This week, the following works have been completed: External plumbing: The sewage and stormwater systems are currently in progress. Tiling: The bathroom area and patio tiling are currently in progress. Kitchen: The kitchen bench has been installed, and the overall kitchen layout is progressing successfully. Light switches, power points and ceiling fans:...
Weekly Update: 3rd – 7th November This week has concluded, and the following works have been completed: External Painting: The granny flat has been painted, giving it a fresh and renewed look. Waterproofing: The bathroom area has been addressed and is now ready for the tiling process. Kitchen Cabinets: The kitchen layout is progressing well and starting to take...
Weekly Update – Week 11 (27th–31st October) Week 11 has concluded, and works have resumed on site.Despite Brisbane’s challenging weather conditions, our teams delivered solid progress. Works Achieved This Week: Bathroom wall pack-out: Wall thickness has been adjusted with new framing to allow waterproofing to take place next week. Fit-outs: Skirting boards, internal window frames,...
Weekly Update – Week 10 (20th–24th October) During Week 10, we faced some challenges which required rescheduling several jobs. As a result, all planned activities for this week have been postponed, and no works were carried out. Plan for Week 11 (27th–31st October): Fit-outs: Scheduled to commence mid-week (around 28th–29th October). Bathroom wall pack-out: Planned for...
Modular Construction on the Rise — Niksen Time Expands into the Sector Modular and prefabricated home construction is rapidly growing across Australia, driven by government programs for social housing, the private sector’s demand for faster project delivery, and stronger support from lenders. At Niksen Time, we joined this movement with our first modular home, which began...
Our week 9 has ended and this is what we achieved: Commencement of painting works:Sanding has been completed, and the next step will involve waterproofing the wet areas along with painting. Continuation of external cladding:Gutter installation has been completed and is ready for downpipe installation. General update:Some works experienced minor delays this week due to sequencing and coordination...