Week 6: Windows, Beadings, and Electrical Works This week, the windows were installed together with the exterior beadings, and the electrical connections for the interior were completed. Next week, works will progress with plumbing, plastering, and painting. The project remains on track, with completion expected by Week 10, towards the end of...
September 2025
Week 5: Roof installation finalised This week, the team successfully completed the roof installation on schedule. The project is progressing well, with no delays to date. With the walls and roof now in place, next week’s works are expected to commence with the rough-in for electrical and plumbing installations, as well as the installation of window frames and exterior panel beadings....
Week 4: Fence Completion, Roof Delivery, and Wall Installation This week, Stage 1 of the fence was completed. Stage 2 will follow, finalising the new boundary fence that will separate the two dwellings. The Bondor roof was delivered, and wall installation commenced on Tuesday. As part of the system, a bottom plate was required to support the wall panels—our team completed the bottom plates on...
Week 3: Slab and Panel Delivery This week, the modular panels were delivered to site. The concrete works for the slab were completed, and the posts for the new fence were poured at the same time. Next week’s works are planned to include completion of the new fence and the erection of walls for the granny...