Weekly Update: 24th – 28th November This week, the internal painting has been completed, and we wanted to share the current progress in a short video: Week 16 Planning: Next week, we will continue installing the bathroom vanities and finalise the internal plumbing and electrical fit-outs. We will continue to keep you updated as the works progress. Kind regards, Niksen Time...
November 2025
Weekly Update: 17th – 21st November This week, the following works have been completed: Bathroom Tiling: Tiling has been completed and the vanities are ready for installation. Patio Tiling: Patio tiling has been finalised. Electrical Works: Conduits for the main and second dwelling have been completed. North Fence: Works have been finalised, and the dividing fence is scheduled to...
Weekly Update: 10th – 14th November This week, the following works have been completed: External plumbing: The sewage and stormwater systems are currently in progress. Tiling: The bathroom area and patio tiling are currently in progress. Kitchen: The kitchen bench has been installed, and the overall kitchen layout is progressing successfully. Light switches, power points and ceiling fans:...
Weekly Update: 3rd – 7th November This week has concluded, and the following works have been completed: External Painting: The granny flat has been painted, giving it a fresh and renewed look. Waterproofing: The bathroom area has been addressed and is now ready for the tiling process. Kitchen Cabinets: The kitchen layout is progressing well and starting to take...