Week 16: Browns Plains Modular Home Update

Weekly Update: 1st–5th December This week, the following works have been completed: Wardrobes:The wardrobes for the two bedrooms have now been installed and finalised. Dividing fence:Construction of the fence dividing the two dwellings has commenced. General electrical works:Tasks including the cooktop installation, electrical conduits for the air-conditioning unit, and the remaining...