Weekly Update – Week 10 (20th–24th October) During Week 10, we faced some challenges which required rescheduling several jobs. As a result, all planned activities for this week have been postponed, and no works were carried out. Plan for Week 11 (27th–31st October): Fit-outs: Scheduled to commence mid-week (around 28th–29th October). Bathroom wall pack-out: Planned for...
modular homes
This week, the plumbing rough-ins have been completed, although some adjustments are still required. Painting and fit-out works have been postponed to next week. Ceiling sheets were delivered on Friday. Week 8 (planned) – Starting on Tuesday 7th (Monday is a Public Holiday) The plan includes: ✓ Adjustments to plumbing rough-ins ✓Fit-outs, and plastering. We’ll keep you informed as soon as...
Week 6: Windows, Beadings, and Electrical Works This week, the windows were installed together with the exterior beadings, and the electrical connections for the interior were completed. Next week, works will progress with plumbing, plastering, and painting. The project remains on track, with completion expected by Week 10, towards the end of...
Week 5: Roof installation finalised This week, the team successfully completed the roof installation on schedule. The project is progressing well, with no delays to date. With the walls and roof now in place, next week’s works are expected to commence with the rough-in for electrical and plumbing installations, as well as the installation of window frames and exterior panel beadings....
Week 4: Fence Completion, Roof Delivery, and Wall Installation This week, Stage 1 of the fence was completed. Stage 2 will follow, finalising the new boundary fence that will separate the two dwellings. The Bondor roof was delivered, and wall installation commenced on Tuesday. As part of the system, a bottom plate was required to support the wall panels—our team completed the bottom plates on...
Week 3: Slab and Panel Delivery This week, the modular panels were delivered to site. The concrete works for the slab were completed, and the posts for the new fence were poured at the same time. Next week’s works are planned to include completion of the new fence and the erection of walls for the granny...
Week 2: Footings and form work This week, the footings were concreted and the formwork was completed. The termite inspection was successfully passed. The slab is now ready for concreting. Works on the slab and the new fence are scheduled to commence next week (Week...
Week 1: Site Preparation and Earthworks This week the site was prepared and earthworks were completed. Due to the ground movement, the existing fence has been compromised and will be replaced. Next week, foundation works will commence with the concreting of the footings and...
At Niksen, we are proud to announce the commencement of our very first modular home construction project this week. The development consists of two dwellings on the same property: Main Dwelling: A one-bedroom home with a study and a bathroom, purchased last year. Secondary Dwelling: A modern two-bedroom, one-bathroom granny flat. This project will span approximately 10 weeks, during which we will...