Weekly Update: 10th – 14th November
This week, the following works have been completed:
External plumbing: The sewage and stormwater systems are currently in progress.
Tiling: The bathroom area and patio tiling are currently in progress.
Kitchen: The kitchen bench has been installed, and the overall kitchen layout is progressing successfully.
Light switches, power points and ceiling fans: Installation started this week and is expected to be completed next week.
Old antenna has also been removed from the site.




Week 14 Planning:
Tiling works will continue, plumbing works will be finalised, internal painting will continue, and the dividing fence will commence along with the remaining section of the fence on the north side.
We will continue to keep you updated as works progress.
Kind regards,
Niksen Time team