Week 16: Browns Plains Modular Home Update

Weekly Update: 1st–5th December

This week, the following works have been completed:

Wardrobes:
The wardrobes for the two bedrooms have now been installed and finalised.

Dividing fence:
Construction of the fence dividing the two dwellings has commenced.

General electrical works:
Tasks including the cooktop installation, electrical conduits for the air-conditioning unit, and the remaining fit-outs have commenced. These will be finalised in Week 17.


Week 17 Planning:

  • Completion of the dividing fence
  • Energex and the electricity supplier to attend site and complete the energisation of the second dwelling
  • Plumbers to finalise their installations and have running water throughout the property

We are getting closer to the completion stage before Christmas.

We will continue to keep you updated as works progress.

Kind regards,

Niksen Time team